c-ts410-2020 question 65 discussion

View all SAP Certified Application Associate - Business Process Integration with SAP S/4HANA 2020 Exam here
back to sap forum

Question 65

What object is always a true Controlling (CO) object?

  • A. Project
  • B. Profit center
  • C. Internal order
  • D. Cost center Most Votes
Answer:

B


User Votes:
A 1 votes
50%
B 12 votes
50%
C 4 votes
50%
D 15 votes
50%
Discussions
0 / 1000
Jboweaver
1 year, 11 months ago

In what Way profit center?

madimxene1097
11 months, 1 week ago

Why not cost center please?

Pacnt1
6 months, 4 weeks ago

In SAP, a cost center is always considered a true Controlling (CO) object.
Explanation: A true CO object means it can be used for actual cost postings and analysis, while a statistical CO object is used for informational purposes only and cannot be directly allocated costs to

psalmizt
5 months, 3 weeks ago

The correct answer is D. Cost centre is considered a true management accounting object.