Question 98

What MRP control parameter defines the scope of a planning run when the system only takes into
account changes that are within the planning? Please choose the correct answer.

  • A. Planning mode
  • B. Processing key - NETCH Most Votes
  • C. Procurement type
  • D. Processing key - NEUPL
Answer:

B


User Votes:
A 16 votes
50%
B 66 votes
50%
C 7 votes
50%
D 10 votes
50%
Discussions
0 / 1000
aphiwe.andisa.radebe
1 year, 10 months ago

Processing key-NETCH

aphiwe.andisa.radebe
1 year, 10 months ago

Processing key - NETCH

molka
1 year, 9 months ago

B. Processing key - NETCH

ngocto170703
1 year, 6 months ago

B. Processing key - NETCH

jonathan
1 year, 6 months ago

a a a a a a a

vytnt1704
1 year, 5 months ago

B - Processing key - NETCH

vytnt1704
1 year, 5 months ago

B - Processing key - NETCH

vytnt1704
1 year, 5 months ago

Thanks for submitting , your comment will be approved soon by our moderators

Fatma
1 year, 3 months ago

Processing key-NETCH

84mqdoan
1 year, 1 month ago

Processing key - NETCH

Lamrinizakaria10
1 year ago

Processing key - NETCH

souleypower
1 year ago

B. Processing key - NETCH

reuter.jessi
10 months, 3 weeks ago

Processing key - NETCH

sharon.adedokun
10 months ago

Processing key - NETCH

Umar
8 months ago

Procurement type

Pacnt1
7 months ago

Processing key - NETCH