crisc question 725 discussion

View all Certified in Risk and Information Systems Control here
back to isaca forum

Question 725 Topic 4

Topic 4
A business unit is updating a risk register with assessment results for a key project. Which of the following is MOST
important to capture in the register?

  • A. Action plans to address risk scenarios requiring treatment
  • B. The team that performed the risk assessment
  • C. An assigned risk manager to provide oversight
  • D. The methodology used to perform the risk assessment
Answer:

D

User Votes:
A 2 votes
50%
B
50%
C
50%
D 1 votes
50%
Discussions
0 / 1000
joeram52
5 days ago

Answer should be A.