Software caba practice test

AnswersCertified Associate Business Analyst Exam


Question 1

-- Exhibit -

-- Exhibit -
Using the "V" Model diagram, what type of testing activity is represented by the letter A?

  • A. Verification or Static
  • B. Validation or Dynamic
  • C. White Box
  • D. Boundary Analysis
  • E. User Acceptance Testing
Answer:

A

Discussions

Question 2

-- Exhibit --

- Exhibit -
Using the "V" Model diagram, what testing phase is represented by the letter C?

  • A. Integration
  • B. Requirements Walkthrough
  • C. User Acceptance Testing
  • D. Unit Testing
Answer:

D

Discussions

Question 3

Exhibit

The diagram is of the ___________ Development Model.

  • A. Waterfall
  • B. Iterative
  • C. Exploratory
  • D. Spiral
  • E. None of the above
Answer:

D

Discussions

Question 4

-- Exhibit -

-- Exhibit -
With regards to Entity Relationship Diagrams, the diagram is a:

  • A. One to one
  • B. One to zero or one
  • C. One to many
  • D. One to zero or many
Answer:

C

Discussions

Question 5

-- Exhibit -

-- Exhibit -
The diagram is a:

  • A. Data Flow Diagram
  • B. Entity Relationship Diagrams
  • C. State Transition Diagram
  • D. USE CASE Diagram
Answer:

B

Discussions

Question 6

-- Exhibit -

-- Exhibit -
The diagram is a:

  • A. Configuration Management Artifacts Map
  • B. Screen Play Script Mapping Diagram
  • C. Use Case Boundary Diagram
  • D. Unit Testing Flow Diagram
  • E. Unit Level Process Map
Answer:

E

Discussions

Question 7

-- Exhibit -

-- Exhibit -
In the table, the number 20.2, which represents the inspection rate, is a:

  • A. Metric
  • B. Correlation Coefficient
  • C. Measure
  • D. Variability Factor
Answer:

A

Discussions

Question 8

-- Exhibit -

-- Exhibit -
In the table, the column labeled "Number of Requirements Inspected" records a:

  • A. Metric
  • B. Correlation Coefficient
  • C. Measure
  • D. Variability Factor
Answer:

C

Discussions

Question 9

Exhibit

In the diagram, the arrow labeled A points to an event on the control chart which is:

  • A. Under Control
  • B. Over Control
  • C. Out of Control
  • D. In Control
  • E. Irrelevant
Answer:

C

Discussions

Question 10

-- Exhibit -

-- Exhibit -
The diagram is of the:

  • A. ISO 9000
  • B. Malcolm Balridge Model
  • C. Capability Maturity Model Integrated
  • D. Process Workbench
  • E. None of the above
Answer:

C

Discussions