Question 1

Which of the following are properties of ECC Multi-Site Planning? (Choose two.)

  • A. Both withdrawal from alternative plant and withdrawal from another plant are defined via special procurement keys.
  • B. The use of scope of planning (cross-plant total planning) is mandatory for Multi-Site Planning.
  • C. When using one-step stock transfer posting, transfer stock is created in the receiving plant.
  • D. When using two-step stock transport order with delivery, the receiving plant is defined as a customer.
Answer:

A, D

Discussions

Question 2

The master data for an in-house production process is to be set up in the SAP ECC system. To do this,
you should create a suitable routing that plans for five operations in an initial sequence (10, 20, 30,
40, 50). There should be an option of relocating operations 30 and 40 to a second sequence on other
work centers if there are capacity bottlenecks. What sequence type would you use to create the
second sequence in the system?

  • A. Substitute sequence
  • B. Alternative sequence
  • C. Parallel sequence
  • D. Standard sequence
Answer:

B

Discussions

Question 3

Which of the following situations occur when a production order is set to Technically Complete
(TECO)? (Choose three.)

  • A. The order and its operations receive the system status Locked (LKD).
  • B. Reservations are deleted.
  • C. Purchase orders for external operations or non-stock materials are deleted.
  • D. The order is no longer relevant for Material Requirements Planning.
  • E. Capacity requirements are deleted.
Answer:

B, D, E

Discussions

Question 4

Which of the following structural elements does a process order have? (Choose three.)

  • A. Item data
  • B. Parallel sequences
  • C. Relationships
  • D. Phases
  • E. Characteristic-based process instructions
Answer:

C, D, E

Discussions

Question 5

Which of the following statements is true for the ATP (available to promise) availability check in SAP
ECC that is triggered from a customer order?

  • A. The ATP check does not confirm against stocks and receipts, it checks consumption against planning requirements.
  • B. An availability check by means of ATP creates fixed links between customer orders and their confirmed receipts.
  • C. The ATP quantity is the quantity still available that can be used to confirm incoming customer orders.
  • D. If the ATP check establishes non-availability, it checks whether it is still possible to procure or produce in time.
Answer:

C

Discussions

Question 6

The company you advise wants to control the availability check in so that when a production and/or
process order is created, the following receipts or issues are taken into account: planned orders,
purchase orders, production orders, reservations, dependent requirements. When the production
and/or process order is released, only the stock that is currently freely usable should be taken into
consideration. How can you fulfill this request?

  • A. Differentiated assignment of two different checking rules in check control.
  • B. Activate the freely usable stock in the scope of check.
  • C. Enter an appropriate availability checking group in the material master.
  • D. Enter an appropriate availability checking rule in the order type.
Answer:

A

Discussions

Question 7

With which functions of the process order can you fulfill the requirements of the Good
Manufacturing Practices (GMP) standard? (Choose three.)

  • A. Material identification and reconciliation
  • B. Availability check
  • C. Batch record
  • D. Resource selection
  • E. Digital signature
Answer:

A, C, E

Discussions

Question 8

An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net
change planning in the planning horizon). The planning horizon is to be set equally for all materials
by default. However, some materials are to be given a different planning horizon.
What procedure would you recommend to the project team for setting the planning horizon on the
system side?

  • A. The planning horizon is set in the MRP groups in Customizing and variant entries are assigned via the plant parameter settings.
  • B. The planning horizon is set in Customizing using the plant parameter setting and variant entries are assigned via the MRP groups for the materials in question.
  • C. The planning horizon is set in the MRP groups in Customizing and the variant values are stored in the material masters for the materials in question.
  • D. The planning horizon is set in the plant parameters in Customizing and variant entries are stored in the material masters for the materials in question.
Answer:

B

Discussions

Question 9

A user you advise wishes to transfer variable process instructions for automated processing directly
to certain work centers and machines in the production department (for example, feed speed,
pressing pressure, dry temperature). The user also wishes to receive variable as-is messages (such as
actual quantities, actual times) from these work centers and machines and to process these
messages for feedback concerning production orders. Which of the following options would you
recommend to implement these requirements?

  • A. Execution Steps (XSteps) and process messages
  • B. SAP Business Intelligence (BI)
  • C. Plant data collection (PP-PDC) interface
  • D. SAP Application Link Enabling (ALE)
Answer:

A

Discussions

Question 10

Which data forms the basis for calculating the capacity requirement for an operation?
(Choose three.)

  • A. Standard values (routing)
  • B. In-house production time (material master)
  • C. Transport time (routing)
  • D. Formulas (work center)
  • E. Operation control key (routing)
Answer:

A, D, E