Question 1

What MRP control parameter defines the scope of a planning run when the system only takes into
account changes that are within the planning? Please choose the correct answer.

  • A. Planning mode
  • B. Processing key - NETCH
  • C. Procurement type
  • D. Processing key - NEUPL
Answer:

B

Discussions

Question 2

Which business processes post to the general ledger? There are 3 correct answers to this question.

  • A. Purchase order creation
  • B. Posting an activity price
  • C. Goods issue from stock
  • D. Depreciation posting
  • E. Posting an activity allocation
Answer:

C, D, E

Discussions

Question 3

Which of the following sequences of the source-to-pay process steps are correct? Please choose the
correct answer.

  • A. 1. Determination of requirements 2. Purchase order handling 3. Handling of payments 4. Goods receipt 5. Invoice verification
  • B. 1. Vendor selection 2. Source of supply determination 3. Purchase order monitoring 4. Goods receipt 5. Handling of payments
  • C. 1. Determination of requirements 2. Vendor selection 3. Purchase order handling 4. Goods receipt 5. Invoice verification
  • D. 1. Source of supply determination 2. Vendor selection 3. Determination of requirements 4. Purchase order handling 5. Goods receipt
Answer:

C

Discussions

Question 4

Which object is created to report on a market segment, such as customer, product and region?
Please choose the correct answer.

  • A. Sales organization
  • B. Profit center
  • C. Primary cost element
  • D. Profitability segment
Answer:

D

Discussions

Question 5

What is the outcome of an automatic payment run? There are 3 correct answers to this question.

  • A. Cleared item in vendor's account
  • B. Financial accounting document
  • C. Open item in vendor's account
  • D. Data prepared for printing
  • E. Approval process initiated
Answer:

A, B, D

Discussions

Question 6

Which objects can be assigned to a profit centers? There are 2 correct answers to this question.

  • A. Material
  • B. Sales organization
  • C. Sales order item
  • D. Operating concern
Answer:

A, C

Discussions

Question 7

Which of the following is the correct hierarchy of organizational structure elements in SAP S/4HANA
(from 1. highest level to 4. lowest level)? Please choose the correct answer.

  • A. 1. Company code 2. Controlling area 3. Organizational unit 4. Operating concern
  • B. 1. Company code 2. Controlling area 3. Sales organization 4. Plant
  • C. 1. Sales organization 2. Plant 3. Division 4. Storage location
  • D. 1. Operating concern 2. Controlling area 3. Company code 4. Plant
Answer:

D

Discussions

Question 8

What is the correct sequence of steps in the sales and distribution process? Please choose the correct
answer.

  • A. 1. Check availability 2. Create sales order 3. Post goods issue 4. Billing
  • B. 1. Create sales order 2. Check availability 3. Process delivery document 4. Post goods issue
  • C. 1. Check availability 2. Create sales order 3. Billing 4. Post goods issue
  • D. 1. Create sales order 2. Check availability 3. Plan transportation 4. Post goods issue
Answer:

B

Discussions

Question 9

Which of the following represents the highest-level unit of all organizational elements in SAP
S/4HANA? Please choose the correct answer.

  • A. Client
  • B. Company code
  • C. Operating concern
  • D. Controlling area
Answer:

A

Discussions

Question 10

What are the main characteristics of SAP S/4HANA? There are 3 correct answers to this question.

  • A. Can be run on any database
  • B. Bring together OLAP and OLTP
  • C. Minor changes are made to the data model
  • D. Simplified applications
  • E. Reduced data footprint
Answer:

B, D, E