SAP c-s4ppm-1909 practice test

SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management Exam


Question 1

For which of the following object types can you define questionnaires?
NOTE: There are 2 correct answers to this question

  • A. Initiative
  • B. Bucket
  • C. Project management project
  • D. Portfolio item
Answer:

A, D

Discussions

Question 2

Where can you define the scheduling type?
NOTE: There are 3 correct answers to this question.

  • A. In customizing
  • B. ON phase level
  • C. On project definition level
  • D. On task level
Answer:

A, C

Discussions

Question 3

What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm In a project
management project?
NOTE: There are 3 correct answers to this question.

  • A. Accounting integration for this project is active
  • B. The project type must allow time recording with the CATS
  • C. The role type must allow time recording with CATS
  • D. The planned efforts is on the task
Answer:

A, B

Discussions

Question 4

You want to distribute capacity requirements in a project management project?
How can you distribute the values?
NOTE: There are 3 correct answers to this question

  • A. Use a distribution function
  • B. Copy values from resource assignments
  • C. Apply a distribution rule
  • D. Update the capacity requirements from the roll-up of task requirements
  • E. Enter the vales manually
Answer:

A, D, E

Discussions

Question 5

What can you use scoring models for?
NOTE: There are 2 correct answers to this question.

  • A. To derive field values of buckets
  • B. Top compare items in reviews
  • C. To compare bucket in reviews
  • D. To derive field values of items
Answer:

B, D

Discussions

Question 6

Which of the following are consequence of releasing a phase?
NOTE: There are 2 correct answers to this question

  • A. Predecessor phases are assigned the status locked
  • B. Lower-level tasks and checklist are release
  • C. Additional tasks cannot be added to the phase
  • D. The phase type is set to read-only
Answer:

B, D

Discussions

Question 7

Which objects can used to record times in Cross-Application Time Sheels (SAP Cats)?
NOTE: There are 3 correct answers to this question

  • A. Phase
  • B. Task
  • C. Role
  • D. Checklist item
Answer:

B, C

Discussions

Question 8

What do you use the check Conflict button for?
NOTE: There are 3 correct answers to this question

  • A. Adjustment of distribution of staffing
  • B. Adjustment of dates of roles
  • C. Adjustment of work according to roles assignment of a task
  • D. Adjustment of work according to resource availability
  • E. Adjustment of dates of staffing
Answer:

A, B, E

Discussions

Question 9

Which of the following are search criteria In Resource Search in Project Management?
NOTE: There are 2 correct answers to this question.

  • A. Work centers
  • B. Organizational units
  • C. Qualifications
  • D. plants
Answer:

B, C

Discussions

Question 10

Which cost planning process can you use at item level?
NOTE: There are 2 correct answers to this question.

  • A. Integrated cost planning
  • B. Hierarchical cost planning
  • C. Manual cost planning
  • D. Rollup of cost planning
Answer:

A, C

Discussions