Question 1
How many different time levels can be selected within one planning view?
A.
Only time levels from the base planning level of selected key figures
B.
All time levels available in the time profile, restricted by global configuration parameter
C.
All time levels available in the time profile
D.
The number of time levels is restricted to four to avoid negative effects on performance
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 2
You need to define a new logic for a key figure to drive values from the PERPRODCUSTREGION level to the PERPRODCUST level. Which of the following configuration options are possible for this process? Note: There are 2 correct answers to this question
A.
Splitting the values from detailed to aggregated level by using a copy operator
B.
Splitting the values from aggregated to detailed level using multiplication by the proportions
C.
Splitting the values form aggregated to detailed level, based on the time profile attribute
D.
Splitting the values from aggregated to detailed level, based on a stored split-factor key figure
Answer:
B, D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 3
You are setting up planning with lot sizes. What are some of the properties of lot sizes that you need to beware of? Note: There are 2 correct answers to this question
A.
Lot sizes are applicable for production and handling quantities.
B.
Periodic lot size setting overrides the minimum lot size.
C.
Lot size are time-independent master data settings
D.
Lot size are applicable for production and transportation quantities
Answer:
C, D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 4
You need to work in two separate sessions for two different SAP IBP tenants. What can help you differentiate the appearance of their user interfaces? Note: There are 2 correct answers to this question
A.
Define a different default planning area via the User Preferences
B.
Have a different set to tiles in the Home group of apps
C.
Set a separate theme for the Home page in the Web UI.
D.
Add the system name and tenant information from the About section to the Home pages
Answer:
B, C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 5
Which Master Data Types are used in time-series-based planning within SAP IBP for response and supply? Note: There are 3 correct answers to this question
A.
DS Order fulfilment
B.
Transportation lane
C.
Customer
D.
Location
E.
Product
Answer:
C, D, E
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 6
You are implementing a demand process in SAP IBP for sales and operations, and consider using the standard forecast key figures available in the sample planning area SAPIBP1. What are the first and last key figures in the logical progression of demand in the S&OP process?
A.
Local Demand Plan first and Combined Final Demand last
B.
Statistical Forecast Qty first and Consensus Demand Plan Qty last
C.
Local Demand Plan first and Consensus Demand Plan Qty last
D.
Statistical Forecast Qty first and Global Demand Plan Qty for SOP last
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 7
What does ABC/XYZ segmentation allow you to do? Note: There are 2 correct answers to this question
A.
Substitute missing values in case of sporadic demands.
B.
Choose time-independent key figures as segmentation measures
C.
Identify inventory items that quire closer attentions
D.
Use forecasting algorithms that are specific to seasonal demands of SKUs in the segment "B"
Answer:
B, C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 8
Which processes are running in sampl to this question.
A.
Supply and Allocation Planning
B.
Inventory Optimization
C.
Response Planning
D.
Demand Sensing
E.
Sales and Operation planning
Answer:
B, D, E
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 9
Which constraints are taken into account by the Time-Series-Based Supply Planning Heuristic (Infinite)? Note: There are 3 correct answers to this question
A.
Adjusted transportation receipts
B.
Aggregated constraints
C.
Maximum lot size
D.
Transportation lead time
E.
Minimum lot size
Answer:
A, D, E
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 10
You are reviewing the master data types that are often used for supply and inventory planning. Which master data types are compound master data types? Note: There are 2 correct answers to this question
A.
SOURCEPRODUCTION
B.
SOURCECUSTOMER
C.
SOURCELOCATION
D.
SOURCECUSTGROUP
Answer:
B, C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 11
Which options can be used to reduce the runtimes of a time-series optimizer run? Note: There are 3 correct answers to this question.
A.
Keep the number of fairshare segments small
B.
Split into multiple planning areas to support weekly vs. daily planning needs.
C.
Use non-overlapping networks by using Subnetworks ID maintained at Location-Products to reduce the size of the problem
D.
Eliminate the usage of telescopic time buckets
E.
Increase the use of incremental lot size beyond the frozen horizon.
Answer:
A, C, D
User Votes:
A
50%
B
50%
C
50%
D
50%
E
50%
Discussions
0/ 1000
Question 12
What is an example of a commonly used time-independent key figure?
A.
A Special key figure marked as an aggregate key figure (aggregate constraint)
B.
A unit of measure key figure, such as UoM Conversion Factor
C.
Any attribute as a key figure
D.
A currency conversion key figure, such as Exchange Rate
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 13
What is an example of a commonly used time-independent key figure?
A.
A Special key figure marked as an aggregate key figure (aggregate constraint)
B.
A unit of measure key figure, such as UoM Conversion Factor
C.
Any attribute as a key figure
D.
A currency conversion key figure, such as Exchange Rate
Answer:
B, C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 14
You are starting a new implementation project for SAP IBP and are considering the possible system architecture. What are the possible approaches for setting up the system landscape? Note: There are 2correct answers to this question
A.
Setup the two-tier landscape and have the configuration for development system regularly — updated from the production system
B.
Create additional planning areas in the test system to support training needs.
C.
Create additional test planning areas in the production system to support cutover needs
D.
Set up a three-tier landscape using transport, starting from the development system to test and — production
Answer:
B, D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 15
What are some of the capabilities of the Planner Workspaces app? Note: There are 2 correct answers to this question.
A.
It supports simulating the effect of the changes
B.
It supports favourites created in SAP IBP, add-in for Microsoft Excel
C.
It supports embedding analytic stories as a workspace component
D.
It supports sharing with other users or user groups.