The project is approaching the end of stage 4 and all work will be completed as planned. The
project manager is now preparing a plan for acceptance and the handover of the 'capability to
provide health and safety training'.
Is this appropriate, and why?
A. Yes, because a plan should be created to measure the number of courses carried out after
project closure.
B. Yes, because a separate closure stage plan should be created during stage 4.
C. No, because closure activities should have been planned at the end of stage 3.
D. No, because user acceptance of the project's products should have taken place throughout
the project.
A
The 'capability to provide health and safety training' has been delivered. During the 'closing a
project' process, the marketing department sent an e-mail to all key customers reminding
them of the deadline to comply with the new government legislation, with an aim to build
relationships with their customers.
Which theme is being applied?
B
CLOSING A PROJECT
The Health and Safety Training Project is part of a strategic program for ABC. The updated
benefits management approach needs to be checked when the products are being handed
over. This check should ensure that it includes appropriate activities to assess whether the
actual course sales meet the agreed forecast in the business case.
Which role should undertake this review as part of the 'closing a project' process?
C
After preparing the stage 3 plan, the project manager left the company. The project board has
decided that, as the stage plan has been agreed, it will not appoint a project manager for stage
3. The team managers will report directly to the project board and will prepare highlight
reports instead of checkpoint reports.
Is this an appropriate tailoring of the roles in the 'managing a stage boundary' process?
D
Explanation:
Reference
https://www.prince2primer.com/the-project-manager-role/
The project is approaching the end of stage 3, and stage 4 is being planned as part of the
'managing a stage boundary' process.
Which action should the project manager carry out as part of the 'update the project plan'
activity?
A
Explanation:
Reference
https://www.prince2primer.com/prince2-2017-update-project-plan-business-case/
MANAGING A STAGE BOUNDARY
The project is approaching the end of stage 3 and the pilot courses have been planned. The
project manager is now undertaking the 'managing a stage boundary' process.
Which action should the project manager undertake as part of the 'update the business case'
activity?
A
The work package to produce the 'updated corporate quality procedures' was created during
stage 3. Before accepting the work package, the team manager produces the team plan and
finds that the expected delivery date is unrealistic. As a result, the project manager agrees an
extra two weeks to complete the work package, within the current stage tolerance. The work
package is then accepted by the team manager.
Is this an appropriate application of the 'manage product delivery' process, and why?
B
MANAGING PRODUCT DELIVERY
Stage 2 is in progress. While producing the team plan, the team manager responsible for the
work package to develop the 'classroom-based training material' discovered that the
representatives assigned to check the products were unsuitable.
Which action should the team manager take in response?
B
The project is in stage 3. Zero time tolerance has been given for this stage. When checking
progress, the project manager noticed that the checkpoint report from the external supplier of
the 'e-learning course' is late. As work package progress information is missing, the project
manager has decided to raise an exception report.
Is this an appropriate action, and why?
A
DRAG DROP
CONTROLLING A STAGE
During stage 4, an issue was raised by an ABC trainer that the classroom-based training
materials contained errors, even though they were signed off during stage 3. They had been
based on materials from a previous course and still contained references to that course. The
impact of this issue is now being assessed.
Here are three actions that were carried out as part of the controlling a stage process.
During which activity (A-F) should each action happen?
Choose only one activity for each action. Each activity can be used once, more than once, or
not at all.
The senior user is concerned that the trainers' limited availability could delay their
accreditation. This was discussed during the 'starting up a project' process, but during the
'initiating a project' process the project manager notices that it has not been recorded.
Which action should the project manager take FIRST?
A
DRAG DROP
INITIATING A PROJECT
Here are three items of information relating to the initiating a project process for the
project.
As part of which activity (A-F) should this information be recorded?
Choose only one theme for each activity. Each theme can be used once, more than once, or
not at all.
The project board has asked user and supplier assurance to review all product descriptions
relating to the 'updated corporate quality procedures', prior to authorizing the stage plan for
stage 3.
Is this appropriate as part of the 'directing a project' process, and why?
D
DRAG DROP
DIRECTING A PROJECT
Here are three activities that occur during the directing a project process.
Which theme (A-E) do they relate to?
Choose only one theme for each activity. Each theme can be used once, more than once, or
not at all.
During stage 3, the team manager reports that the work to update the 'corporate quality
procedures' has been completed and the product is ready to be delivered.
What should project assurance do next?
C