pmi pmp practice test

Project Management Professional

Last exam update: Dec 13 ,2025
Page 1 out of 40. Viewing questions 1-15 out of 595

Question 1

A project is starting its second iteration out of six. During the daily meeting, a team member asks for
help. In order to finish a deliverable, an
approval from the design department will be needed.
What should the project manager do?

  • A. Meet with the design manager to ask for the necessary approval.
  • B. Invite a design team member to the next daily meeting.
  • C. Update the issue log and escalate it to the project sponsor.
  • D. Replace this iteration deliverable for one without any blockers.
Mark Question:
Answer:

B


Explanation:
Inviting a design team member to the next daily meeting facilitates direct communication and
collaboration, which is in line with Agile principles. This approach promotes quick resolution of issues
and supports the iterative nature of Agile project management, where cross-functional team
collaboration is key to delivering value in each iteration1.
: = The iterative project management process emphasizes the importance of collaboration and
transparency to address pain points and avoid stagnation of progress1. Additionally, the issue log is a
tool for tracking and managing issues, but it does not replace the need for direct communication and
immediate action when possible2

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 2

A project manager has been assigned to lead an IT project to store information on sold lottery tickets.
During the project execution, a failure in the
system caused 10 numbers to be sold two times. This happened during the month of greatest
demand because the prize was the highest of the
year. The project team is concerned that one of those tickets could be the winner.
What should the project manager do first?

  • A. Reassure the sponsor by explaining the probability of this risk materializing is extremely low.
  • B. Carry out tests to verify that the system does not fail again due to the high occurrence of events.
  • C. Review the list of risks to verify that this issue was considered and execute the detailed action plan.
  • D. Inform the sponsor about the issue and make a request for sufficient funds to be made available.
Mark Question:
Answer:

C


Explanation:
In the context of PMP objectives and the PMBOK guide, the first action in response to an identified
risk, such as the sale of duplicate lottery numbers, is to review the project’s risk management plan.
This plan should include previously identified risks and their corresponding response strategies. If the
issue of duplicate numbers was anticipated, the project manager should follow the established
action plan to address it. This aligns with the PMBOK’s emphasis on proactive risk management,
which includes planning for risks and having response strategies ready to implement when
needed123.
Reference:
Project Risk Management According to the PMBOK1
The Standard for Risk Management in Portfolios, Programs, and Projects2
Risk Management Process for PMP® - Project Management Academy3

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 3

A project manager is working on an agile project in a changing business environment. The project
sponsor is worried about benefits realization
and asks the project manager to pay attention to changes that can affect the project.
Which action should the project manager take to identify changes that may affect the product?

  • A. Implement face-to-face communication between the team and product owner to change the iteration objectives as needed.
  • B. Stop the iteration as soon as possible in case an external change that makes the product invaluable is identified.
  • C. Take action to reprioritize the backlog after every iteration to evaluate if user stories are still valuable to the business.
  • D. Apply a pair programming technique to react to changes immediately, even in the middle of the interaction.
Mark Question:
Answer:

C


Explanation:
In an agile project, it is crucial to continuously assess the project’s direction and priorities to ensure
alignment with business objectives and adapt to changes in the business environment. Reprioritizing
the backlog after every iteration allows the project manager and the team to evaluate the value and
relevance of user stories in light of any new developments or changes. This practice ensures that the
project remains focused on delivering the most valuable features to the business and can adapt to
changes quickly and efficiently.
: (Professional in Business Analysis Reference Materials source and documents)
A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
The PMI Guide to Business Analysis
Business Analysis for Practitioners: A Practice Guide

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 4

In a geographically distributed team, a developer continues to delay a coding activity. This activity is
on the critical path. The project manager
found out that the delay is due to the developer's lack of understanding of the customer
requirements shared by the off-site team.
What should the project manager do?

  • A. Replace the developer with a skilled resource.
  • B. Perform a root cause analysis (RCA) with the team members.
  • C. Facilitate communication to ensure clarification of the requirements.
  • D. Conduct frequent performance reviews.
Mark Question:
Answer:

C


Explanation:
In a situation where a developer is delaying a critical path activity due to a lack of understanding of
customer requirements, the project manager should facilitate communication to ensure clarification
of the requirements. This approach aligns with the best practices in project management and
business analysis, which emphasize the importance of clear communication and understanding of
stakeholder requirements for project success. By clarifying the requirements, the developer can gain
a better understanding of what is expected and proceed with the coding activity, thus mitigating the
delay on the critical path.
Reference:
PMI’s Guide to the Project Management Body of Knowledge (PMBOK® Guide) emphasizes the
importance of stakeholder engagement and effective communication to ensure that project
requirements are understood and met1.
The PMI Professional in Business Analysis (PMI-PBA)® highlights the role of communication in
business analysis, including the need for clarity and the avoidance of misunderstandings23.
Discussions among PMP professionals also suggest that once a root cause analysis is performed and
the issue is identified, the next step is to address the issue directly, which in this case involves
clarifying the requirements1.

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 5

A project scope statement has been approved, and the project manager and core team have been
assigned to the project. Suddenly, the project
manager takes a temporary leave of absence due to a medical emergency. While the project
manager is on leave, the team develops the project
schedule. When the project manager returns, a detailed schedule is almost complete.
What should the project manager do?

  • A. Ensure that the schedule is aligned with the vision and objectives.
  • B. Escalate the compliance issue to the project management office (PMO).
  • C. Congratulate the team and move on to the execution phase.
  • D. Develop a new detailed schedule with the team and project sponsor.
Mark Question:
Answer:

A


Explanation:
When a project manager returns from an absence to find a nearly complete project schedule
developed by the team, the priority should be to ensure that the schedule aligns with the project’s
vision and objectives. This is crucial because the project scope statement, which includes the
project’s vision, objectives, and work breakdown structure, guides all project activities. The project
manager must review the developed schedule against the approved project scope statement to
ensure that all project work aligns with the documented objectives and deliverables. If discrepancies
are found, the project manager should work with the team to make necessary adjustments. This
approach helps maintain the project’s integrity and ensures that the final deliverables will meet the
stakeholders’ expectations.
: (Based on the Project Management Professional (PMP) guidelines and standards from PMI’s
resources123

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 6

A project manager manages a bridge construction project. The project manager has received a major
change request from a regulatory stakeholder to add one branch of the bridge to the engineering
design. The project manager prepared a change request, which was reviewed and accepted by the
change control board (CCB).
What should the project manager do now?

  • A. Notify the project team about the change request's approval.
  • B. Include the new branch of the bridge in the design.
  • C. Communicate the decision to the stakeholder who requested the change.
  • D. Evaluate the adjustments to the project management plan.
Mark Question:
Answer:

C


Explanation:
After a change request is approved by the Change Control Board (CCB), the project manager should
communicate the decision to the stakeholder who requested the change. This is an important step in
the change management process as it ensures transparency and maintains trust with stakeholders. It
also allows the stakeholder to understand that their request has been considered and integrated into
the project, which is crucial for stakeholder engagement and satisfaction.
: = The information is aligned with the PMBOK Guide’s Change Management Process, which
emphasizes the importance of communication with stakeholders after a decision has been made on a
change request1. Additionally, the role of Business Analysts in change management includes
ensuring that changes align with the organization’s goals and objectives, which involves
communicating approved changes to relevant stakeholders2.

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 7

A project is near completion but it is behind schedule. The contingency budget has already being
used, although the remaining budget should be
enough to complete the project. The only subject matter expert (SME) assigned to the project has
been asked by their manager to solve a
problem in the operations department.
What should the project manager do?

  • A. Escalate the situation to the project sponsor.
  • B. Free the resource to handle the operations priority.
  • C. Ask the manager to submit a change request.
  • D. Design a negotiation strategy for this situation.
Mark Question:
Answer:

D


Explanation:
In this scenario, the project manager should engage in negotiations to address the conflict of
resource allocation. The PMBOK Guide suggests that project managers should possess negotiation
skills to resolve such conflicts effectively. By negotiating, the project manager can work towards a
solution that satisfies the needs of the operations department while also ensuring the SME’s
contributions to the project are not lost, thus keeping the project on track.
: The response is based on general project management principles as outlined in the PMBOK Guide
and conflict resolution strategies that include negotiation, which are part of the PMP’s body of
knowledge.

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 8

A project manager assigned to an education project needs to train a workforce in application
development. The customer is responsible for
providing the training center, and the deadline to start the first training is in 2 weeks. The customer
calls to say that the center will not be available
in 2 weeks due to some unforeseen problems.
What should the project manager do next?

  • A. Apply the terms and conditions of the contract with penalties.
  • B. Issue a change request to reflect the anticipated date for training.
  • C. Help the customer find an alternative location to start the training.
  • D. Update the project schedule with the new date for training.
Mark Question:
Answer:

C


Explanation:
In situations where unforeseen problems prevent the planned execution of a project, the project
manager should focus on problem-solving and collaboration to keep the project on track. According
to the PMBOK® Guide, the project manager’s responsibilities include engaging with stakeholders to
meet project requirements and creating customer satisfaction1. The Professional in Business Analysis
Reference Materials also emphasize the importance of collaboration and stakeholder engagement to
address issues and find solutions2. Therefore, helping the customer find an alternative location
aligns with the project manager’s role in facilitating project success and maintaining stakeholder
satisfaction. Reference:
PMBOK® Guide – Seventh Edition, Project Management Institute1.
Professional in Business Analysis Reference Materials, PMI2.

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 9

Knowledge sharing has been a key priority for a complex technological project with a large number
of team members. During the project
execution phase, the project manager receives numerous complaints from all team members that
they are overloaded with knowledge-sharing
emails, which contain useful information but are unmanageable due to the high volume.
What should the project manager do to solve this problem?

  • A. Establish an unofficial communications method for the team to share knowledge and lessons learned.
  • B. Establish a pull communications method to access knowledge repositories and lessons learned.
  • C. Establish an interactive communications method between stakeholders to share knowledge and lessons learned.
  • D. Establish a push communications method for the team to share knowledge and lessons learned.
Mark Question:
Answer:

B


Explanation:
In the scenario described, the project team is overwhelmed by the volume of knowledge-sharing
emails, which indicates that the current method of communication is not effective. A pull
communication method allows team members to access information as needed, rather than being
bombarded with emails. This method enables team members to manage their time and resources
more effectively by seeking out knowledge when it is convenient for them, thus reducing the
overload and improving the manageability of information.
Reference: The solution aligns with best practices in project management communication strategies,
where pull communication is recommended in situations where information overload is an
issue. This approach is supported by resources on project management communication methods,
which suggest that pull communication can help alleviate the problem of information overload by
allowing team members to access information on demand1234.

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 10

A client wants to create an innovative software for the travel industry using an agile approach. A
project manager from the company was assigned
to work on the details and estimates as requested by the client.
What should the project manager do before sending the information to the client?

  • A. Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.
  • B. Sequence the tasks with estimates and add standard risk reserves to use for software development.
  • C. Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.
  • D. Work with the team to understand their views and add the appropriate dependencies and risks.
Mark Question:
Answer:

D


Explanation:
In an agile project, collaboration and team input are crucial for success. Before sending details and
estimates to the client, the project manager should engage with the team to gather their insights and
expertise. This ensures that the project plan reflects a realistic approach, considering the team’s
views on dependencies and potential risks. Agile methodologies emphasize the importance of team
collaboration and iterative development, which includes regularly revisiting and adjusting plans as
the project progresses1234.
Reference:
Agile Communication: Techniques, Examples and Best Practices1
How to Nail Your Agile Communication Plan2
How to Communicate and Collaborate with Stakeholders in Agile Projects3
The Agile Project Management Approach4
V

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 11

According to this burnup chart for the last 7-day sprint, what should the project lead address with the
product owner and team?

  • A. The product owner should not ask the team to change their sprint commitments.
  • B. The team is accepting too much work in the sprint after it has started.
  • C. The team is not meeting the expectations of the product owner.
  • D. The team should have stopped on day 4 and started a new sprint.
Mark Question:
Answer:

C


Explanation:
The burnup chart indicates that the “Completed” work is trailing behind the “Scope,” suggesting
that the team is not meeting the expectations set by the product owner. This discrepancy can be due
to various factors such as underestimation of tasks, unforeseen challenges, or scope changes. It’s
important for the project lead to address this with the product owner and team to realign
expectations, reassess the workload, and implement corrective actions to ensure that project goals
are met within the sprint timeframe.
Reference:
A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
The PMI Guide to Business Analysis
Business Analysis for Practitioners: A Practice Guide12345.

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 12

After the merger of two large companies, a project manager is assigned to a project. The company
hires a consultant to ensure best practices are
being used in information security. During an iteration, the consultant requests changes to a software
component, claiming that it is not meeting
market requirements.
What should the project manager do?

  • A. Continue the iteration and add the requested changes.
  • B. Continue the iteration and review the change with the customer.
  • C. Cancel the iteration and meet with the product owner.
  • D. Cancel the iteration and add the requested changes.
Mark Question:
Answer:

B


Explanation:
When a consultant requests changes to a software component during an iteration, claiming it does
not meet market requirements, the project manager should continue the iteration and review the
change with the customer. This action ensures that the iteration’s progress is not halted while also
addressing the consultant’s concerns. It is essential to involve the customer in the decision-making
process since they have a vested interest in the product’s success and alignment with market needs.
This approach is consistent with the principles of stakeholder engagement and communication found
in both PMP and business analysis best practices.
Reference:
The PMBOK® Guide, which outlines the project management framework, emphasizes the importance
of stakeholder engagement and communication throughout the project life cycle1.
The PMI Professional in Business Analysis (PMI-PBA)® guide highlights the role of business analysts in
facilitating communication between stakeholders and ensuring that project outcomes align with
business needs23.
Discussions among PMP professionals suggest that addressing changes without disrupting the
current iteration’s workflow is a common practice, and customer involvement is crucial

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 13

Two members of a new project team disagree on the best approach to solve a problem. The conflict
has been going on for 1 week. The two
members are tense around each other and are taking everything personally.
What should the project manager do?

  • A. Help the team members to resolve the conflict in a way that results in the best team performance.
  • B. Offer a compromise that is acceptable to both team members, even if it may not be the best solution.
  • C. Understand each team member's argument and select the one that results in less risk to the project.
  • D. Send both team members to the human resources (HR) department for an acceptable resolution.
Mark Question:
Answer:

A


Explanation:
In situations where team members disagree, it is essential for the project manager to facilitate a
resolution that leads to the best team performance. This involves understanding the perspectives of
each team member, fostering a collaborative environment, and guiding the team towards a solution
that aligns with the project’s goals. The project manager should employ conflict resolution
techniques such as problem-solving and collaboration, which are recommended by the PMBOK
Guide. These techniques encourage open communication, ensure that all voices are heard, and work
towards a consensus that supports the project’s objectives and enhances team performance.
: (Based on the conflict resolution strategies outlined in the PMBOK Guide and other PMP
resources12.)

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 14

A project to construct an electricity generation plant is on site near a nature reserve. An
environmental activist group is questioning the need for
the project. The customer has informed the project manager to disregard the group as they are not in
support of the project.
What should the project manager do next?

  • A. Ask the customer to contact the activist group and let them know the project status and completion date.
  • B. Add the activist group to the list of stakeholders and analyze the impact they may have on project delivery.
  • C. Obey the directive from the customer since they are funding the project and are the most important stakeholder.
  • D. Request the project team disregard all communication from the activist group and continue with their project work.
Mark Question:
Answer:

B


Explanation:
The PMBOK® Guide emphasizes the importance of identifying all stakeholders and understanding
their influence and impact on the project. In this scenario, the environmental activist group, being
concerned with the project’s proximity to a nature reserve, qualifies as a stakeholder. Their concerns
could impact project delivery, public perception, and regulatory compliance. Therefore, the project
manager should add the group to the stakeholder list and analyze their potential impact as part of
the stakeholder engagement process12. This aligns with the principles of stakeholder management
and engagement, which are crucial for project success and are also reflected in the Professional in
Business Analysis (PBA) reference materials, where managing stakeholder expectations and
engagement is a key aspect of business analysis34.
: = This response is informed by the PMBOK® Guide’s approach to stakeholder management12, as
well as the practices outlined in the Professional in Business Analysis reference materials regarding
stakeholder engagement and management34.

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 15

A project manager is leading a project that is in the execution phase. Due to a company
reorganization, some key project team members are likely to leave the project.
What should the project manager do next?

  • A. Discuss this issue with the affected team members and support them during the transition.
  • B. Start looking for replacements as soon as possible to help prevent any schedule slippage.
  • C. Engage with the project sponsor to ensure that this change does not affect the project execution.
  • D. Determine the impact to the project and implement mitigations per the project management plan.
Mark Question:
Answer:

D


Explanation:
When facing the potential departure of key project team members, a project manager should first
evaluate the situation’s impact on the project’s scope, schedule, cost, and quality. The next step is to
refer to the project management plan, which should include a risk management plan with
predefined mitigation strategies for such scenarios. Implementing these mitigations will help to
manage the changes effectively and keep the project on track.
: The response is based on general project management principles as outlined in the PMBOK Guide
and the standard practices of risk and change management that are part of the PMP’s body of
knowledge.

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000
To page 2