Question 1

The probability and impact matrix is primarily used to:
A. Quantify risk issues for trends during a quality audit.
B.Develop a risk register for risk planning.
C.Evaluate each risks importance and priority during Perform Qualitative Risk Analysis.
D.Define risk and compare impacts during Perform Quantitative Risk Analysis.

Answer:

C
186/186

Discussions

Question 2

Which of the following is an output of Close Procurements?

  • A. Accepted deliverables B.Organizational process assets updates C.Managing stakeholder expectations D.Performance reports
Answer:

B

Discussions

Question 3

Which of the following is a statistical concept that calculates the average outcome when the future
includes scenarios that may or may not happen?

  • A. Sensitivity analysis B.Three-point estimate C.Modeling and simulation D.Expected monetary value analysis
Answer:

D

Discussions

Question 4

Which of the following is a tool and technique used to monitor risk?

  • A. Technical performance measurement 185/186 Questions & Answers PDF P- B.Cost performance baseline C.Benchmarking D.Cost of quality
Answer:

A

Discussions

Question 5

A project manager has created an issue log to document issues communicated by project team
members during weekly team meetings. This is an input of:

  • A. Manage Stakeholder Expectations. B.Monitor and Control Risks. C.Plan Risk Management. D.Report Performance.
Answer:

A

Discussions

Question 6

Which of the following can be used as an input for Define Scope?

  • A. Product analysis B.Project charter C.Scope baseline D.Project scope statement
Answer:

B

Discussions

Question 7

At which stage of team development do members begin to work together, adjust work habits, and
trust each other?

  • A. Forming B.Storming C.Norming D.Performing
Answer:

C

Discussions

Question 8

The group technique that enhances brainstorming with a voting process used to rank the most useful
ideas for prioritization is called the:

  • A. majority rule technique. 184/186 Questions & Answers PDF P- B.nominal group technique. C.Delphi technique, D.idea/mind mapping technique.
Answer:

B

Discussions

Question 9

Which of the following is an estimating technique that uses the values of parameters from previous
similar projects for estimating the same parameter or measure for a current project?

  • A. Reserve analysis B.Three-point estimating C.Parametric estimating D.Analogous estimating
Answer:

D

Discussions

Question 10

When cost variance is negative and schedule variance is positive, the project is:

  • A. under budget and behind schedule. B.over budget and ahead of schedule. C.on schedule. D.complete; all planned values have been earned.
Answer:

B