The probability and impact matrix is primarily used to:
A. Quantify risk issues for trends during a quality audit.
B.Develop a risk register for risk planning.
C.Evaluate each risks importance and priority during Perform Qualitative Risk Analysis.
D.Define risk and compare impacts during Perform Quantitative Risk Analysis.
C
186/186
Which of the following is an output of Close Procurements?
B
Which of the following is a statistical concept that calculates the average outcome when the future
includes scenarios that may or may not happen?
D
Which of the following is a tool and technique used to monitor risk?
A
A project manager has created an issue log to document issues communicated by project team
members during weekly team meetings. This is an input of:
A
Which of the following can be used as an input for Define Scope?
B
At which stage of team development do members begin to work together, adjust work habits, and
trust each other?
C
The group technique that enhances brainstorming with a voting process used to rank the most useful
ideas for prioritization is called the:
B
Which of the following is an estimating technique that uses the values of parameters from previous
similar projects for estimating the same parameter or measure for a current project?
D
When cost variance is negative and schedule variance is positive, the project is:
B