What term represents the desired state of the organization achieved after transition?
D
Which of the following statements about the information management plan are true?
1. It describes the techniques to be used to maintain programme information
2. It sets out a timetable for establishing naming conventions
A
Reference: https://repmt.com/learning-paths/msp-managing-successful-programmes/
Which risk management perspective is concerned with a programmes interdependencies with other
initiatives?
A
Reference: https://www.simplilearn.com/overview-of-risk-and-issue-management-tutorial
Which is MOST likely to lead to the re-definition and re-scoping of a programme?
C
What role has a focus on designing benefit measures within a programme to track business
performance against targets?
A
What role authorizes improvements to the wording of the Vision Statement in order to provide
greater clarity for stakeholders?
D
Which is a transformational flow process?
D
Reference: https://www.simplilearn.com/transformational-flow-overview-tutorial
Which transformational flow process results in the achievement of outcomes?
B
Reference:
https://www.cxproject.co.uk/uploads/62/Managing_Successful_Programmes_Process_Model.pdf/
Which document informs and directs identifying a Programme and Defining a Programme?
B
Reference: https://www.simplilearn.com/identifying-a-programme-tutorial
Which role is responsible for developing the programme’s governance framework?
B
Reference: https://www.simplilearn.com/governance-themes-and-transformation-flows-tutorial
Which is a programme management principle?
A
Reference: https://www.simplilearn.com/programme-management-principles-tutorial
Which information about a project should be included in the Projects Dossier?
A
Reference: https://community.simplilearn.com/threads/what-is-project-dossier.211/
Which of the following statements about successful stakeholder engagement are true?
1. It is more active and embracing than communication.
2. It includes stakeholders in decision making and implementation.
C
Reference: https://www.axelos.com/news/blogs/february-2019/stakeholder-engagement-what-and-
why
Which is a response option to an identified threat?
B
Which role focuses on monitoring the progress of the programme at a strategic level?
A. Sponsoring group
B. Programme manager
C. Senior responsible owner
D. Risk manager
B
(none)
Explanation
Reference: https://www.simplilearn.com/delivering-the-capability-tutorial