Question 1
Whose approval is needed to replace a Stage Plan with an Exception Plan?
A. Corporate orprogramme management
B. Project Board
C. Project Manager
D. Team Manager
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
nbho123
6 months, 1 week ago
project board
Question 2
Which is a recommended quality review team role?
A. Project Manager
B. Assurance
C. Project Support
D. Administrator
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 3
Which is a purpose of an End Project Report?
A. Identify individuals or groups that need to be told that the project is coming to an end
B. Review how well the project performed against the Project Initiation Documentation used to authorize it
C. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
D. Ensure that key project information is archived and made secure
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 4
Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.
A. Project Assurance
B. Project Support
C. the risk actionee
D. the risk owner
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 5
Which is a FALSE statement about technical stages?
A. Can overlap with other technical stages
B. Typified by the use a particular set of specialist skills
C. Include the Managing a Stage Boundary process activities
D. Can span more than onemanagement stage
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 6
Which is a purpose of the Starting up a Project process?
A. Provide information so a decision can be made asto whether a project is viable and worthwhile to initiate
B. Define the means of communication between the project and corporate or programme management
C. Define the project controls
D. Record any identified risks in the Risk Register
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 7
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
A. Onlycorporate or programme management
B. Only the Project Board
C. Only the Project Manager
D. All levels of management
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 8
Which is a purpose of the Risk Register?
A. Describe the risk management techniques and standards to be applied to the project
B. Act as a central record of information relating to the identified risks for the project
C. Act as a repository forinformal issues
D. List the responsibilities for achieving an effective risk management procedure
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 9
Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?
A. Managing Product Delivery
B. Initiating a Project
C. Managing a Stage Boundary
D. Starting up a Project
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 10
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity
A. Avoid
B. Reduce
C. Share
D. Transfer
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 11
Which is a task of product-based planning?
A. Identify activities and dependencies
B. Write the Project Product Description
C. Prepare the Work Packages
D. Produce Product Status Accounts
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 12
Which role is responsible for creating Checkpoint Reports?
A. Senior Supplier
B. Team Manager
C. Change Authority
D. Project Support
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 13
How many management stages should a PRINCE2 project consist of?
A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
B. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
C. Initiation stage and at least one other management stage to cover the remainder of the project
D. Start up stage, initiation stage and a closing stage
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 14
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
A. project cost tolerance
B. stage cost tolerance
C. Work Package cost tolerance
D. product cost tolerance
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 15
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
project board