When can a process be rated as 'Largely achieved' for a particular attribute of that process?
C
Which of the following statements about the Process performance indicators and the Process
capability
indicators are true?
1 Process capability attribute indicators apply to capability levels 1 to 5.
2 Process performance indicators apply to capability levels 1 to 5.
B
Which attribute is associated with an established process?
A
What Change Enablement component in the Implementation Life Cycle supports the defining of the
target
state?
B
What Programme Management component in the implementation Life Cycle is linked to embedding
the new approaches?
A
What term is used to describe changes in the enterprise's internal and external environment caused
by a
recent merger with another enterprise?
D
What term is used to describe how a governance implementation should not be perceived as an
isolated
project?
D
Which information should a business case include?
B
What is the name of the Change Enablement life cycle Phase which supports 'Phase 4 -What needs
to be
done'?
A
In what order does the Management of Enterprise IT occur in the СОВIT 5 Process Reference Model?
B