iSQI ctfl-syll2018 practice test

ISTQB Certified Tester Foundation Level Exam


Question 1

An issue has been found in a production system, where a code component fails to release memory
after it has finished using it. Which of the following tools would have been the MOST effective at
detecting this defect during Performance testing?
A. Dynamic analysis tool.
B. Test Execution tool.
C. Configuration management tool.
D. Coverage measurement tool.
101/102
Questions & Answers PDF
P-

Answer:

A
102/102

Discussions

Question 2

Your agile project has scheduled a final sprint before release to fix and re-test all open defects with a
priority level of 3 or above.
The following defect report shows the defect fields that are currently being captured on the system.
Title: Unable to add excursions to pre-paid cruises
Date raised: 21/05/18
Author: Emma Rigby
Status: Fixed
What occurred: I went to book an excursion for a pre-paid cruise but received an error message
saying, Facility not available. I can book excursions on cruises that have not yet been fully paid.
What should have occurred: Requirement 3.12 says clearly that customers can add excursions after
cruises have been fully paid so the facility should have been available (when an additional amount
may now need to be paid).
Priority: 2
Software build: 2.1
Test level: System test
Environment details: System test 3
Which of ONE of the following additional defect report fields would be MOST beneficial for the sprint
team to add?

  • A. Severity.
  • B. Test Script Id.
  • C. Actual results.
  • D. Expected results.
Answer:

A

Discussions

Question 3

Which of the following are product risks?
a) Failure prone software delivered.
b) Software does not perform its intended functions.
c) Insufficient staff available for testing.
d) Test environment not ready on time.
100/102
Questions & Answers PDF
P-
e) Poor data integrity and quality.

  • A. b, c and e.
  • B. b, d and e.
  • C. a, b and e.
  • D. b, c and d.
Answer:

C

Discussions

Question 4

Which of the following BEST describes how configuration management supports the test process?

  • A. It enables the tester to reproduce the tested item through unique identification and version control.
  • B. It enables the tester to systematically design test conditions, cases and data.
  • C. It enables incidents to be tracked from discovery and classification to correction and confirmation of the solution.
  • D. It helps the test manager to decide how best to integrate and coordinate the testing activities into the software life cycle.
Answer:

A

Discussions

Question 5

Which of the following would NOT typically be covered in a test summary report?

  • A. The risks associated with unresolved defects found during testing.
  • B. Any features of the system that were not tested along with reasons.
  • C. Whether there is any economic benefit in continuing testing beyond the planned date.
  • D. An analysis of lessons learned to determine changes for future projects.
Answer:

C

Discussions

Question 6

99/102
Which one of the following statements about techniques for estimating test effort is correct?

  • A. The metrics-based technique finds the most similar former project and uses its original estimate for the current project.
  • B. The expert-based approach is based on the experience of the owners of the testing tasks or by subject matter experts.
  • C. The metrics-based technique uses metrics supplied by the current test team based on their subjective feel for effort required.
  • D. In an expert-based approach, the test lead with the most years in the role is chosen to produce the estimate.
Answer:

B

Discussions

Question 7

Tests have been specified for the latest software release and users have prioritised these.
However, there are some dependencies between tests as shown in the table below (e.g. Test ID.
123 cannot be run until Test ID. 456 has been successfully completed).

Which test execution schedule best meets the prioritisation and dependency conditions?

  • A. 3, 5, 7, 10, 2, 4, 6, 8, 9, 1.
  • B. 5, 7, 4, 3, 9, 10, 1, 6, 8, 2.
  • C. 6, 1, 2, 9, 4, 3, 5, 7, 8, 10.
  • D. 1, 4, 3, 5, 2, 7, 9, 10, 6, 8.
Answer:

D

Discussions

Question 8

Which of the following are benefits of an independent test team, and which are drawbacks?
a) Independent testers can find different defects.
b) Developers may put less emphasis on quality.
c) Independent testers can be seen as the reason for delayed projects.
d) Independent testers can verify assumptions made during the specification of a system.

  • A. a and b are benefits, c and d are drawbacks.
  • B. b and c are benefits, a and d are drawbacks.
  • C. a and d are benefits, b and c are drawbacks.
  • D. c and d are benefits, a and b are drawbacks.
Answer:

C

Discussions

Question 9

Which of the following BEST describes a methodical approach to the Error Guessing test technique?
A. A tester dynamically designs and executes tests based on their knowledge, exploration of the test
item and the results of previous tests.
B. An experienced tester makes a list of potential defects and failures, and designs and runs tests to
generate these failures should the defects be present in the code.
C. A tester designs, implements and executes tests to cover test conditions found in checklists that
are based on what is important for the user.
D. An inexperienced tester is asked to attempt to guess errors that may have been missed by
experienced testers during formal test design.

Answer:

A
98/102

Discussions

Question 10

Which of the following is an approach that can be used for exploratory testing?

  • A. Time-boxed test sessions are created, during which a tester uses a test charter containing test objectives to guide the testing.
  • B. A tester methodically executes tests from a list of possible failures, based on experience, defect and failure data.
  • C. A tester analyses, designs and implements tests based on external rules and standards.
  • D. Tests are designed based on the guidance of stakeholders and experts outside the test team.
Answer:

D

Discussions
To page 2