Question 1

At the Initiative Horizon, we see the concept of adaptive planning expressed when a solution owner:

  • A. Ensures technical documentation is updated in response to changes
  • B. Seeks guidance and direction from senior stakeholders for remaining work
  • C. Uses feedback to make decisions about remaining solution components or initiatives
  • D. Meets with stakeholders to gather feedback about delivered solution components
Answer:

C

Reference:
https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf
(29)

Discussions

Question 2

The team is struggling with how to best design and explore options for moving forward. They settle
on a time-boxed research approach which is often referred to as a:

  • A. Simulation
  • B. Wasteful
  • C. Spike
  • D. Incremental
Answer:

C

Reference:
https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf
(99)

Discussions

Question 3

The team is considering which of several solution paths they should invest in. They are working only
from conjecture and opinion, not data and facts. A practitioner with an agile mindset would remind
them to:

  • A. Perform a value analysis of real options
  • B. Discover what works by trying things out
  • C. Consider analysis at multiple horizons
  • D. Collaborate more to create new ideas
Answer:

C

Reference:
https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf
(24)

Discussions

Question 4

Good analysis practices at the Strategy Horizon facilitate the transfer of relevant knowledge between
teams to:

  • A. Better understand what features will be delivered
  • B. Cancel initiatives that no longer provide value
  • C. Stimulate collaboration and continuous improvement.
  • D. Prioritize and sequence features for delivery
Answer:

C

Reference:
https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf
(38)

Discussions

Question 5

The team is discussing what analysis performed at the initiative level should include. They realize this
analysis will support a number of key decisions, particularly decisions around the:

  • A. Needs and the solution that will satisfy those needs
  • B. Objectives and strategies to meet those objectives
  • C. Problem and the system that will address that problem
  • D. Strategy and identifying actions that will address that strategy
Answer:

A

Discussions

Question 6

While using Kano Analysis to determine what features to include in the MVP, the delivery team
decides to include characteristics which if omitted will cause intense dissatisfaction. A team member
indicates that these are referred to as:

  • A. Performance characteristics
  • B. Threshold characteristics
  • C. Minimum characteristics
  • D. Excitement characteristics
Answer:

B

Reference:
https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf
(74)

Discussions

Question 7

The team is discussing the initiative and thinking about what solution increments are worth doing.
An appropriate technique for them to use is:

  • A. Backlog refinement
  • B. Portfolio kanban
  • C. Purpose alignment model
  • D. Story elaboration
Answer:

B

Reference:
https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf
(39)

Discussions

Question 8

While reviewing criteria for a well-written story, the team discusses the following criteria:

  • A. Detailed persona characteristics
  • B. Cost-benefit valuation
  • C. Alignment to the organization’s vision statement
  • D. Achievable unit of development
Answer:

D

Reference:
https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf
(55)

Discussions

Question 9

During a backlog refinement meeting, the team uses the appropriate technique to focus discussion
on backlog items and their:

  • A. Technical designs and related details
  • B. Related users, user goals, user activities and their importance
  • C. Estimates determined by the delivery team
  • D. Resource requirements and availability for work.
Answer:

D

Discussions

Question 10

Through ongoing collaboration with stakeholders the team continues to uncover new information.
This is leading to changes to the products that are being produced. The team should:

  • A. Stop all work until stakeholders can decide what they need
  • B. Schedule additional review sessions to speed up stake holder decisions
  • C. Accept all changes but delay additional solution development work to minimize rework
  • D. Continue as is since the process is working
Answer:

B