GAQM csm-001 practice test

Certified Scrum Master (CSM) Exam

page 1 out of 6

Viewing questions 1-15 out of 82


Question 1

Please select which statement is the most accurate:

  • A. Agile Development is an implementation of Scrum
  • B. Scrum is an implementation of Agile Development Scrum é uma implementação do Desenvolvimento Ágil
  • C. Agile Development and Scrum are synonyms for the same methodology
  • D. Agile Development and Scrum are contrasting methodologies
Answer:

B

Discussions
0 / 1000

Question 2

When should the Product Owner ship or implement a Sprint increment?

  • A. At the end of every Sprint
  • B. When the Team feels is done with every Sprint
  • C. Whenever the increment is free of defects
  • D. When it makes sense
Answer:

D

Discussions
0 / 1000

Question 3

The correct sequence of events in using Scrum framework is as follows:

  • B. Sprint Planning, Sprint, Daily Scrum, Sprint Review, and Sprint Retrospective
  • C. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
  • D. Sprint Planning, Daily Scrum, Sprint, Sprint Review, and Sprint Retrospective
Answer:

B

Discussions
0 / 1000

Question 4

You are the Scrum Master and your Development Team of 6 members has completed six Sprints with
thefollowing information:
Sprint 1: 10 pontos
Sprint 2: 11 pontos
Sprint 3: 15 pontos
Sprint 4: 14 pontos
Sprint 5: 15 pontos
Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate number
ofSprintrequired to complete product development?

  • A. 6
  • B. 5
  • C. 4
  • D. 3
Answer:

B

Discussions
0 / 1000

Question 5

Which statement below best describes the primary objective of the Sprint Retrospective?

  • A. The primary objective of the Sprint Retrospective is to identify what went wrong or hindered the Sprint
  • B. The primary objective of the Sprint Retrospective is to provide feedback to the Product Owner(s).
  • C. The primary objective of the Sprint Retrospective is to recommend ways to work better in the Sprint
Answer:

C

Discussions
0 / 1000

Question 6

Which of the following statements best explains what the term Sprint means in Scrum?

  • A. A sprint is a specific amount of days for a team to test and resolve any issues prior to product release orshipment
  • B. A sprint is a specific amount of days for a team to work at a sustainable pace to finish select work.
  • C. A sprint is an agreed upon period of time for team members to select individual items from the productbacklog to work on.
  • D. A sprint is a specific amount of days for a team to work as many hours as needed to finish assigned work
Answer:

B

Discussions
0 / 1000

Question 7

The Sprint planning meeting is comprised of how many sections?

  • A. 4
  • B. 3
  • C. 2
  • D. 1
Answer:

C

Discussions
0 / 1000

Question 8

What is the major difference between Product Backlog and Sprint Backlog?

  • A. The Product Backlog is equal to the Sprint Backlog
  • B. The Product Backlog is a subset of the Sprint Backlog
  • C. The Sprint Backlog is a subset of the Product Backlog
  • D. The Sprint Backlog is owned by the Product Owner
Answer:

C

Discussions
0 / 1000

Question 9

What happens when the Sprint is cancelled?

  • A. The Scrum Team disbands immediately
  • B. The complete Sprint Backlog is put back to the Product Backlog
  • C. The completed Sprint Backlog items are evaluated for a release and incomplete items are discarded
  • D. The completed Sprint Backlog items are evaluated for a release and incomplete items are put back to theProduct Backlog
Answer:

D

Discussions
0 / 1000

Question 10

Which of the following is not a Scrum artifact?
Qual dos seguintes no um artefato Scrum?

  • A. User Stories
  • B. Sprint Backlog
  • C. Product Backlog
  • D. Incremento de Software
Answer:

A

Discussions
0 / 1000

Question 11

Who is on the Scrum Team?

  • A. Project Manager
  • B. Project Owner
  • C. Product Owner
  • D. Development Team
  • E. Manager
  • F. CEO
  • G. Scrum Master
Answer:

C,D,G

Discussions
0 / 1000

Question 12

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

  • A. Methods of communication
  • B. The way the Scrum Team does Sprint Planning
  • C. Skills needed to improve the Development Team's ability to deliver
  • D. Its Definition of Done
  • E. All of the above
Answer:

E

Discussions
0 / 1000

Question 13

What is the maximum time that Scrum recommends the team spend in the daily scrum (daily
standup)?

  • A. Fifteen minutes
  • B. Thirty minutes
  • C. One hour
  • D. Four hours
  • E. As long as ittakes
Answer:

A

Discussions
0 / 1000

Question 14

Which three questions are answered by all Development Team members at the Daily Scrum?

  • A. What work am I going to do today?
  • B. Why were you late?
  • C. What impediments are in the way of my accomplishing my work?
  • D. What work did I do yesterday?
  • E. How is the Sprint proceeding?
Answer:

A,C,D

Discussions
0 / 1000

Question 15

What is the maximum amount of time a sprint retrospective should take?

  • A. 1 hour
  • B. 1 and half hour
  • C. 3 hours, for an 30 days Sprint
Answer:

C

Discussions
0 / 1000