Page 1 out of 47. Viewing questions 1-15 out of 704
Question 1
Which document defines how a project is executed, monitored and controlled, and closed?
A.
Strategic plan
B.
Project charter
C.
Project management plan
D.
Service level agreement
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 2
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?
A.
Risk and uncertainty increase; the cost of changes increases.
B.
Risk and uncertainty increase; the cost of changes decreases,
C.
Risk and uncertainty decrease; the cost of changes increases.
D.
Risk and uncertainty decrease; the cost of changes decreases.
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 3
Which tool or technique is used in the Plan Scope Management process?
A.
Document analysis
B.
Observations
C.
Product analysis
D.
Expert judgment
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 4
Which tool or technique is an examination of industry and specific vendor capabilities?
A.
Independent estimates
B.
Market research
C.
Analytical techniques
D.
Bidder conferences
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 5
An input used in developing the communications management plan is:
A.
Communication models.
B.
Enterprise environmental factors.
C.
Organizational communications,
D.
Organizational cultures and styles.
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 6
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
A.
Expert judgment
B.
Forecasting methods
C.
Earned value management
D.
Analytical techniques
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 7
The Perform Quality Assurance process occurs in which Process Group?
A.
Executing
B.
Monitoring and Controlling
C.
Initiating
D.
Planning
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 8
Enterprise environmental factors are an input to which process?
A.
Control Scope
B.
Define Scope
C.
Plan Scope Management
D.
Collect Requirements
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 9
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
A.
Identify Risks
B.
Control Risks
C.
Plan Risk Management
D.
Plan Risk Responses
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 10
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
A.
Plan Schedule Management.
B.
Develop Project Charter.
C.
Develop Schedule.
D.
Plan Scope Management.
Answer:
A
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 11
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?
A.
Issue log
B.
Change log
C.
Expert judgment
D.
Change requests
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 12
An input to the Plan Stakeholder Management process is:
A.
The project charter.
B.
The stakeholder analysis.
C.
A communication management plan.
D.
A stakeholder register.
Answer:
D
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 13
An input to the Plan Cost Management process is:
A.
Cost estimates.
B.
Resource calendars,
C.
The project charter,
D.
The risk register.
Answer:
C
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 14
A technique used to determine the cause and degree of difference between baseline and actual performance is:
A.
Product analysis.
B.
Variance analysis.
C.
Document analysis,
D.
Decomposition.
Answer:
B
User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
0/ 1000
Question 15
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as: