A project team member highlights to the project manager that expensive licensing for critical software in use across the
project may expire before the completion project.
Which of the following would the project manager MOST likely do?
A
A project manager is starting a project on an unfamiliar technology. The document that is MOST likely to be created and
distributed is an:
C
A new stakeholder has requested the status and progress reports for the project milestones. Which of the following
documents should the project manager address FIRST?
C
Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to
have a tablet instead of a laptop.
Which of the following steps should the project manager take NEXT?
A
A vendor is late with product deliverables. Which of the following documents should the PM refer to FIRST?
C
Collaboration tools are BEST used instead of email when multiple people are:
D
Explanation:
Collaboration tools allow project team members to work on the same documents while maintaining version control so only
the most recent document is available for review. For example, you might post an SOW and alert your team members that
youd like
them to review and make their additions and changes to the document. The collaboration tool provides a check-in and
check-out process so that team members are always reviewing and updating the latest version of the document.
Which of the following shows projected project expenditures?
A
While starting a new project, management is aligning the project to the organization's strategy, assigning limited resources
based upon priorities, and optimizing resource deployment between projects.
Which of the following BEST describes these actions?
A
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides,
determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as:
A
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200
Which of the following project phases occurs when requirements are detailed?
C