Consider an information system of a Pay-Tv company based on a SOA architecture.
The integrated system currently consists of three core systems:
- a CRM (Customer Relationship Management) system
- a BRM (Billing and Revenue Management) system
- a CAS (Conditional Access System) system
all of them communicating with SOA Middleware.
You have been asked to manage the testing activities for the integration of two additional off-the-
shelf systems from two different vendors: a SMS (Short Message Service) server and an IVR
(Interactive Voice Response) system.
Assume that there is a high likelihood that the two off-the-shelf systems will be low-quality and that
you have a clear proof that the testing performed by the two vendors on their systems has been
unsystematic and unprofessional. This obviously leads to higher quality risk for the overall integrated
system.
You are the Test Manager of this project. Your main goal is to plan for testing activities to mitigate
this risk.
Which of the following answers best describes the test activities (assuming it is possible to perform
all of them) you should plan for?
Number of correct responses: 1

  • A. You should plan for an informal and minimal acceptance test of the two off-the-shelf systems and then a single end-to-end test of the overall integrated system
  • B. You should directly plan for a single end-to-end test focused on end-to-end tests of the overall integrated system without an acceptance test of the two off-the-shelf systems
  • C. You should plan for two levels: a system integration test and an end-to-end test of the overall integrated system
  • D. You should plan for adequate re-testing of both the systems followed by a system integration test and an end-to-end test of the overall integrated system
Mark Question:
Answer:

D

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 2

Assume you are the Test Manager for a new software release of an e-commerce application.
The server farm consists of six servers providing different capabilities. Each capability is provided
through a set of web services.
The requirements specification document contains several SLAs (Service Level Agreements) like the
following:
SLA-001: 99.5 percent of all transactions shall have a response time less than five seconds under a
load of up-to 5000 concurrent users
The main objective is to assure that all the SLAs specified in the requirements specification document
will be met before system release. You decide to apply a risk-based testing strategy and an early risk
analysis confirms that performance is high risk. You can count on a well-written requirements
specification and on a model of the system behavior under various load levels produced by the
system architect.
Which of the following test activities would you expect to be the less important ones to achieve the
test objectives in this scenario?
Number of correct responses: 1

  • A. Perform unit performance testing for each single web service
  • B. Monitor the SLAs after the system has been released into the production environment
  • C. Perform system performance testing, consisting of several performance testing sessions, to verify if all the SLAs have been met
  • D. Perform static performance testing by reviewing the architectural model of the system under various load levels
Mark Question:
Answer:

B

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 3

The following is the unique “critical” quality risk item that has been identified:
CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to
get the number of bottles from the user
Test analysis for system testing has just begun and the following test conditions have been identified:
TC-SEL-2. Test the selection of the package sizes
TC-SEL-4. Test wrong numbers of bottles for an order
TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles
from the user
What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and
EXCR2 exit criteria?
Number of correct responses: 1

  • A. 4
  • B. 3
  • C. 2
  • D. 1
Mark Question:
Answer:

A

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 4

The following are the requirements identified as “critical”:
REQ-SEL-001. The user shall be able to combine all the three products with all the four durations to
define an item to purchase
REQ-SEL-002. The user shall be able to add a maximum of six different items to the shopping cart
REQ-PUR-001. The user shall be able to purchase all the items in the shopping cart using a credit
voucher
REQ-PUR-002. The user shall be able to purchase all the items in the shopping cart using the
available credit already charged on the smartcard
REQ-PUR-003. The user shall be able to purchase all the items in the shopping cart using all the
accepted credit cards (Visa, MasterCard and Great Wall Card)
REG-LOGO-001. The user shall be able to logout (by clicking the logout button) from both the “select”
and “purchase” pages going back to the “browse” page (anonymous navigation)
Moreover the following quality risk item has been identified as “critical”:
QR-P1. The web customer portal might not be able to provide the expected response time (less than
10 sec) for the purchase transactions under a load of up-to 1000 concurrent users
Test analysis for system testing has just begun and the following test conditions have been identified:
TC-SEL-01. Test the combinations of products and durations to define an item to purchase
TC-SEL-02. Test the maximum number of items, which can be added to the shopping cart
TC-PUR-01. Test the purchase of an item
TC-PUR-02. Test the purchase of an item with the credit charged on the smartcard
What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and
EXCR2 exit criteria?
Number of correct responses: 1

  • A. 1
  • B. 2
  • C. 3
  • D. 4
Mark Question:
Answer:

C

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 5

Which of the following statements describing the consequences of specifying test conditions at a
detailed level is NOT true?
Number of correct responses: 1

  • A. In an environment where the test basis is continuously changing, it is recommended to specify test conditions at a detailed level in order to achieve a better maintainability
  • B. The specification of test conditions at a detailed level can be effective when no formal requirements or other development work products are available
  • C. The specification of test conditions at a detailed level can require the implementation of an adequate level of formality across the team
  • D. For system testing, the specification of test conditions at a detailed level, carried out early in the project as soon as the test basis is established, can contribute to defect prevention
Mark Question:
Answer:

A

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 6

The following is the unique “critical” quality risk item that has been identified:
CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to
get the number of bottles from the user
Test analysis for system testing has just begun and the following test conditions have been identified:
TC-SEL-2. Test the selection of the package sizes
TC-SEL-4. Test wrong numbers of bottles for an order
TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles
from the user
Assume that you have used traceability to determine the logical test cases that cover all the
requirements and the single risk item identified in that scenario.
Which of the following is a positive logical test that is complete and correct, and covers the REQ-SEL-
4 requirement?
Number of correct responses: 1

  • A. Select a 6-bottles package, then try to insert 5 bottles; verify that no error messages are displayed
  • B. Select a 6-bottles package, then try to insert 7 bottles; verify that no error messages are displayed
  • C. Select a 6-bottles package, then try to insert 7 bottles; verify that the "Invalid number of bottles" message is displayed
  • D. Select a 6-bottles package, then try to insert 7 bottles
Mark Question:
Answer:

C

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 7

The following are the requirements identified as “critical”:
REQ-SEL-001. The user shall be able to combine all the three products with all the four durations to
define an item to purchase
REQ-SEL-002. The user shall be able to add a maximum of six different items to the shopping cart
REQ-PUR-001. The user shall be able to purchase all the items in the shopping cart using a credit
voucher
REQ-PUR-002. The user shall be able to purchase all the items in the shopping cart using the
available credit already charged on the smartcard
REQ-PUR-003. The user shall be able to purchase all the items in the shopping cart using all the
accepted credit cards (Visa, MasterCard and Great Wall Card)
REG-LOGO-001. The user shall be able to logout (by clicking the logout button) from both the “select”
and “purchase” pages going back to the “browse” page (anonymous navigation)
Moreover the following quality risk item has been identified as “critical”:
QR-P1. The web customer portal might not be able to provide the expected response time (less than
10 sec) for the purchase transactions under a load of up-to 1000 concurrent users
Test analysis for system testing has just begun and the following test conditions have been identified:
TC-SEL-01. Test the combinations of products and durations to define an item to purchase
TC-SEL-02. Test the maximum number of items, which can be added to the shopping cart
TC-PUR-01. Test the purchase of an item
TC-PUR-02. Test the purchase of an item with the credit charged on the smartcard
Assume that you have used traceability to determine the logical test cases that cover all the
requirements and the single risk item identified in that scenario.
Which of the following is a positive logical test that is complete, is correct, and covers the REG-LOGO-
001 requirement?
Number of correct responses: 1

  • A. On the purchase page (“purchase state”), click the logout button; verify that the browse page (“browse state”) is displayed
  • B. On the select page (“select state”), click the logout button
  • C. On the purchase page (“purchase state”), click the logout button; verify that the “Impossible to logout – complete or cancel the current transaction” message is displayed
  • D. On the browse page (“browse state”), click the logout button
Mark Question:
Answer:

A

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 8

You are not confident with the assessment of the risk level and you suspect that it will be possible to
find high-priority bugs in low-risk areas.
Furthermore the period for test execution is very short. Your goal is to test all the product risks in a
risk-based way, while assuring that each product risk gets at least some amount of testing.

Which of the following answers describes the best test execution schedule in this scenario?
Number of correct responses: 1

  • A. T1, T2, T3, T4, T5, T6, T7, T8, T9, T10
  • B. T1, T3, T5, T7, T9, T2, T4, T6, T8, T10
  • C. T10, T9, T8, T7, T6, T5, T4, T3, T2, T1
  • D. T10, T8, T6, T4, T2, T9, T7, T5, T3, T1
Mark Question:
Answer:

B

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 9

You are following a risk-based testing strategy. The test execution time is very limited. Assume that
all the product risk items require more or less the same level of test effort.

Which of the following answers describes the best execution schedule in this scenario?
Number of correct responses: 1

  • A. 1- Test the acceptance of transactions coming from the IVR channel 2- Test the correct charge of the Smart Card with the required contents 3- Test the correct pre-activation of the Smart Card 4- Test the correct activation of the Smart Card
  • B. 1- Test the correct pre-activation of the Smart Card 2- Test the correct charge of the Smart Card with the required contents 3- Test the correct activation of the Smart Card 4- Test the acceptance of transactions coming from the IVR channel
  • C. 1- Test the correct activation of the Smart Card 2- Test the correct pre-activation of the Smart Card 3- Test the correct charge of the Smart Card with the required contents 4- Test the acceptance of transactions coming from the IVR channel
  • D. 1- Test the correct pre-activation of the Smart Card 2- Test the correct activation of the Smart Card 3- Test the correct charge of the Smart Card with the required contents 4- Test the acceptance of transactions coming from the IVR channel
Mark Question:
Answer:

D

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 10

Assume that the following test cases have been executed at the end of the first week of test
execution: TC-001, TC-002 and TC-007. All these tests are ‘passes’.
What is the MINIMUM number of the remaining test cases that must be successfully executed to
fulfill the EX1 exit criteria?

Number of correct responses: 1

  • A. 4
  • B. 5
  • C. 6
  • D. 7
Mark Question:
Answer:

A

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 11

Assume that no additional product risks have been identified during the first week of test execution.


Which of the following answers would you expect to best describe the residual risks associated with
the identified product risks, at the end of the first week of test execution?
Number of correct responses: 1

  • A. Since R3 is the only risk for which all test cases have passed, the risk has been reduced by 20%
  • B. The test execution status table indicates that the risk has been reduced by 56%
  • C. The residual risk level can’t be determined, because it requires that all the test cases have been executed
  • D. The test execution table doesn’t give an indication of the risk level of the open defects and the test cases that failed or are not run yet
Mark Question:
Answer:

D

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 12

The following are the exit criteria described in the test plan of a software product:
EX1. The test suite for the product must ensure that at least each quality risk item is covered by at
least one test case (a quality risk item can be covered by more test cases).
EX2. All test cases in the test suite must be run during the execution phase.
EX3. Defects are classified into two categories: “C” (critical defect) and “NC” (non-critical defect). No
known C defects shall exist in the product at the end of the test execution phase.
Which of the following information is useless when the specified exit criteria is evaluated?
Number of correct responses: 1

  • A. A traceability matrix showing the relationships between the product risk items and the test cases
  • B. A list of all the open defects with the associated classification information extracted from the defect tracking system
  • C. A chart, showing the trend in the lag time from defect reporting to resolution, extracted from the defect tracking system
  • D. The execution status of all the test cases extracted from the test management tool
Mark Question:
Answer:

C

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 13

Which of the following is an example of the test closure activity indicated as "lessons learned"?
Number of correct responses: 1

  • A. Archive all the test results of the acceptance testing phase
  • B. Deliver a list of the open defects of a software product released into production to the service desk team
  • C. Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects
  • D. Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing
Mark Question:
Answer:

C

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 14

A chart showing the trend in the lag time from defect reporting to resolution during system testing is
also available. The chart shows that the daily closure period is consistently and significantly above
the rolling closure period for a long period of the system testing phase.
Almost all defects found during system testing have been related to the system as a whole, not
related to single units or integrations issues. Almost all quality risks have been addressed during the
unit and integration testing phase and no residual quality risks were present in the integrated
system. This has been confirmed by exploratory testing sessions performed during system testing,
targeted at finding defects in these quality risk areas.
Based on the given information only, which one of the following areas would you expect to be
considered more in the retrospective meeting in order to be improved?
Number of correct responses: 1

  • A. The requirements review
  • B. The defect management process
  • C. The quality risk analysis process
  • D. The system design and architecture design reviews
Mark Question:
Answer:

B

User Votes:
A
50%
B
50%
C
50%
D
50%
Discussions
vote your answer:
A
B
C
D
0 / 1000

Question 15

You can count on well-written requirements, but you can’t count on an adequate contribution of the
stakeholders to the quality risk analysis. You have to mitigate the insufficient contribution of the
stakeholders because the risk-based testing approach shall minimize the product risks. Your test
team has one expert tester in security testing.
Which of the following test activities would you expect to be the less important in this context?
Number of correct responses: 1

  • A. Extract from the defect tracking system of the previous project all the security defects and failures, and classify them to support design and execution of specific tests
  • B. Automate all functional and non-functional system tests
  • C. Apply systematic and exploratory testing for integration and system test
  • D. Perform exploratory testing sessions with adequate charters covering security aspects
Mark Question:
Answer:

B

User Votes:
A
50%
B
50%
C
50%
D
50%