Question 1

A contract management plan is a subsidiary of what other type of plan?
A. Resource plan
B. Project management plan
C. Cost control plan
D. Expected monetary value plan

Answer:

B
169/169

Discussions

Question 2

In which process might you use risk reassessment as a tool and technique?

  • A. Qualitative risk analysis
  • B. Risk monitoring and control
  • C. Monitor and control project work
  • D. Risk response planning
Answer:

B

Discussions

Question 3

Which process uses occurrence probability and impact on project objectives to assess the priority of
168/169
Questions & Answers PDF
P-
identified risks?

  • A. Risk identification
  • B. Qualitative risk analysis
  • C. Risk management planning
  • D. Quantitative risk analysis
Answer:

B

Discussions

Question 4

When can pre-assignment of project team members occur?

  • A. When the project uses capital expenditures.
  • B. When the required staff can be acquired from outside sources.
  • C. When the project would be ignored due to travel expenses.
  • D. When the project is the result of specific people being promised as part of a competitive proposal.
Answer:

D

Discussions

Question 5

Which illustrates the connection between work that needs to be done and its project team
members?

  • A. Work breakdown structure
  • B. Network diagrams
  • C. Staffing management plan
  • D. Responsibility matrix
Answer:

D

Discussions

Question 6

Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work-days.
What should be your concern?

  • A. There is a cost under run.
  • B. There is a cost overrun.
  • C. May not meet deadline.
  • D. The project is 20 days behind schedule.
Answer:

B

Discussions

Question 7

Which estimating technique uses the actual costs of previous similar projects as a basis for
estimating the costs of the current project?
167/169
Questions & Answers PDF
P-

  • A. Analogous
  • B. Parametric
  • C. Bottom-up
  • D. Top-down
Answer:

A

Discussions

Question 8

Fast tracking is a schedule compression technique used to shorten the project schedule without
changing project scope.
Which of the following can result from fast tracking?

  • A. The risk of achieving the shortened project time is increased.
  • B. The critical path will have positive total float.
  • C. Contingency reserves are released for redeployment by the project manager.
  • D. Duration buffers are added to maintain a focus on planned activity durations.
Answer:

A

Discussions

Question 9

Which of the following is a schedule network analysis technique that takes limited resources into
account?

  • A. Network reserve analysis
  • B. Critical chain method
  • C. Lead and lag adjustment
  • D. Critical path method
Answer:

B

Discussions

Question 10

Which of the following is the correct network diagram for the table?
166/169
Questions & Answers PDF
P-

  • A. Begin - A - C - D - E - End - B - D
  • B. Begin - A - B - C - D - E - End
  • C. Begin - A - B - D - E - End A - C - D
  • D. Begin - A - C - D - E - End - B - C
Answer:

A

Discussions